Schedule (Gantt)

Menu → Production → Schedule (Gantt)

The Schedule (Gantt) shows the plan of order operations on a timeline - a separate row for each machine, line and stage without a resource. The planner moves operations with the mouse, locks them, plans unplanned operations manually or runs automatic planning, whose result is a proposal to compare and approve. The resource calendar (shifts, holidays, maintenance) is shown in the timeline background, and the actual lot execution below the plan.

The plan does not change the order or operation status - the status is set by shop floor events. The plan affects the queue order in the Operator panel, the order forecast end and the material reservation.


Access and permissions

The Schedule (Gantt) item is in the Production menu in the OmniMES context. The administrator grants access in Access permissions.

  • Moving operations, changing the plan and locks require write permission for the Schedule (Gantt) or Production orders screen.

  • Plan automatically and Recalculate from now require write permission for the Schedule (Gantt) screen.

  • Without these permissions the schedule is view-only (“View only — no permission to change the plan.”).

Toolbar

Element

Action

Today + 2 days, Week, 2 weeks

Length of the visible period.

Arrows and Today

Previous and next range; back to today. Next to them - the visible date range.

Resources planned in the period

By default the timeline shows the resources planned in the visible period. You can choose specific machines and lines from the list.

Stages without resource

Shows the rows of stages without a resource (e.g. curing).

Legend

Explains the colours, borders and icons.

Refresh

Reloads the plan. The timeline refreshes itself every 60 seconds.

Plan automatically

Opens automatic planning.

How to read the schedule

Marking

Meaning

Operation background colour

Product colour.

Hatched start

Changeover before the operation.

Neutral / orange / red / purple border

Order due date not at risk / at risk / overdue / order completed after its due date.

Dashed border

Draft order (not released).

Padlock

Locked - automatic planning does not move the operation.

Red glow and triangle

Collision - the operation overlaps another one on the same resource.

Outline and ban icon

Material blocked - the operation needs material that is only in quarantine or blocked.

Box icon

Material short.

Thin bar below the plan

Actual lot execution.

Item with sparkles

Plan proposal (preview).

Red line

Now.

Row background

Resource calendar: Outside shifts, Holiday / day off, Maintenance, Planned stop, Extra shift.

Hovering over an operation shows the order, product, operation status, order due date, plan, changeover and material availability.

Changing the plan on the timeline

  • Drag an operation to change its time or move it to another resource of the same type (machine to machine, line to line).

  • The edge of an operation changes its length (in 5-minute steps).

  • Ctrl + mouse wheel zooms the timeline in and out.

  • Clicking an operation opens its details, and clicking a resource name - the resource capacity in the visible period.

The plan of a locked, running, paused, done or skipped operation and of an operation of a closed or cancelled order cannot be changed.

Operation details

The details panel shows the operation and order status, due state, priority, collision and material availability, and below: order, product, stage, resource, quantity, good / scrap, order due date, plan, changeover, norm (with its source) and execution.


  • Lock - a locked operation is not moved by automatic planning or by dragging on the timeline.

  • Operation plan - Planned start and Planned end. An empty planned end means that the system calculates the end from the norm and the resource calendar. Save plan saves the change, Remove from plan moves the operation to the Unplanned operations list.

  • Lots in execution - lots working on this operation in the visible period of the timeline.

  • Open order - goes to the order details.

When the operation needs blocked material, the panel shows a red message with the list of materials and the Recalculate from now button (described below).

Resource capacity

Clicking a resource name opens the Capacity dialog: Available (time from the resource calendar - shifts and exceptions - in the visible period), Planned (operations planned in this time), Free and Utilization.

Unplanned operations

Below the timeline is the Unplanned operations list - operations of open orders that have no plan yet: order with priority, stage, product, resource, material Availability, quantity and due date.

  1. Click Plan manually next to the operation.

  2. Choose the resource and enter the Planned start. The system calculates the plan end from the norm and the resource calendar.

  3. Click Plan.

Automatic planning

Automatic planning arranges the operations of open orders by priority and due date, in the first free gaps of the resources, taking calendars, norms and changeovers into account. The result is a proposal - the plan changes only after approval. It is simple forward planning with finite capacity, not APS-class optimisation.

  1. Click Plan automatically.

  2. Set the Frozen window (operations that start within this time from now stay where they are) and the Planning horizon (days from now). The defaults come from the module settings.

  3. Click Create proposal.

  4. Compare the proposal with the current plan and click Approve plan or Reject.


Plan comparison shows the indicators of the current plan and of the proposal. A green mark shows the better value.

Indicator

Meaning

Late orders

Number of orders that will finish after their due date.

Total delay [h]

Sum of order delays.

Setups [min]

Total changeover time.

Plan end

When the last operation ends.

Unplanned operations

Operations that did not get a plan.

Planned operations with blocked material

Planned operations whose material is only in quarantine or blocked.

Unplanned — material blocked

Operations that the proposal leaves unplanned because of material.

Open orders

Number of open orders.


Below the comparison is the Changed operations list (current plan and proposal for each operation) and the number of unchanged operations: locked, in progress and in the frozen window.

  • Show on timeline - preview of the proposal below the plan of each resource (items with sparkles and a dashed border). The banner above the timeline has Back to comparison and Hide preview.

  • Approve plan - saves the operation plan from the proposal. Operations changed after the proposal was created are skipped (the message gives the number of applied operations and conflicts).

  • Reject - the plan stays unchanged.

  • New proposal - back to the parameters.

The dialog also shows Recent proposals with their status: Proposal, Approved, Rejected or Superseded. Show proposal opens the comparison of an earlier proposal. A proposal saved in the What-if planner app has a Proposal with what-if assumptions box above the comparison that lists the assumptions (resource down, extra work, priority, due date).

Approving a proposal with what-if assumptions

Below the assumptions box there is a Save together with the plan section. Select what should change together with the operation plan so that the next planning run takes the assumptions into account too:

Option

Default

What it saves

Enter downtimes and extra shifts in the resource calendar

selected

A resource downtime as a Maintenance exception, extra work as an Extra shift, with the note “from plan proposal #…”. A window that is already in the calendar is not duplicated.

Change order priorities

selected

Order priorities from the assumptions - like a change in the order edit, with an entry in the order history.

Change order due dates

not selected

Order due dates from the assumptions, with an entry in the order history. An order due date is usually the date agreed with the customer - change it only when the customer has accepted the new date.

Only the options for assumptions the proposal has are shown. With nothing selected, the calendar and orders stay unchanged - approving then saves only the operation plan.

The plan, the calendar and the orders are saved together or not at all. When an assumption cannot be saved - e.g. the order is already completed or cancelled, someone changed its priority or due date after the proposal was created, or the resource was deleted - the dialog shows a message with the order number and nothing changes. Then clear that option or prepare a new proposal. New calendar exceptions appear in the Event log (event Calendar exception from a plan proposal), and priority and due date changes - in the order history.

Proposals do not pile up: when you create a new one, your older open proposals beyond the five newest get the Superseded status, and so do open proposals older than 7 days. Superseded proposals older than 30 days are deleted. Approved and Rejected ones (a planner's decision) stay as the plan history.

Planning rules:

  • Locked operations, operations in progress and operations in the frozen window stay where they are.

  • The other operations are arranged by order priority and due date; on a tie, the order without a changeover goes first.

  • An operation goes into the first free gap of the resource according to the calendar. A stage without a resource has unlimited capacity.

  • The changeover comes from the setup matrix (product colour or family change) or from the norm.

  • Material: an operation whose material is only in quarantine or blocked stays unplanned (Unplanned — material), and the next stages of that order - with the note Unplanned — waits for an earlier stage. This also applies to operations in the frozen window. Approval removes the plan of such operations. A plain material shortage (without quarantine and holds) does not stop planning - it is shown as a warning.

Blocked material and “Recalculate from now”

When the plan has operations that need material only in quarantine or blocked, a red banner appears above the timeline - “Material blocked: … planned operations need material that is only in quarantine or blocked.” - and the operations get an outline and a ban icon.

Recalculate from now (on the banner and in the operation details) creates a new planning proposal calculated from the present moment and opens the comparison right away. Operations with blocked material stay unplanned in it until the quality decision. The planner approves the proposal as usual.

Material availability is calculated by the same function as in the order and in the operator panel - the tags are described in the Production orders chapter, section “Materials”. Lot quality statuses are described in the Lots and genealogy and Quality chapters.

What-if planner (plan variants)

The What-if planner app answers questions such as: what happens to due dates if a machine stops for 8 hours, will an extra Saturday on a line recover late orders, what if an order gets the Urgent priority or an earlier due date. It runs the same automatic planning as Plan automatically, but saves nothing - the shop-floor plan changes only after a proposal is approved in the Schedule.

The app is installed by a superuser or a user with access to the App Studio: the “What-if planner” app panel below the Schedule timeline → Install app. It goes to the Studio menu in the Production planning section, shared with the groups that see the Schedule. When a newer version is available, the panel shows Update app. It also works in Claude Desktop (MCP Apps) - there it only calculates and does not save proposals.

  1. Add a variant (+ Variant) and name it, e.g. “Press down for 8 h”.

  2. Add assumptions (several per variant are allowed):

    • Resource down (breakdown, maintenance) - a machine, a line (together with its machines) or the whole plant, start and duration; the resource does not work in that window,

    • Extra shift - an extra working window of the resource (e.g. Saturday 6-14),

    • Order priority - a new priority of an open order,

    • Order due date - a new due date; due-date indicators are then measured against the new date.

  3. Click Compare variants (up to 5 variants at a time; the base variant without assumptions is always calculated).

The KPI comparison has the columns Current plan, Base (the plan automatic planning would build now) and your variants. The indicators are the same as in the proposal comparison. The colour and the number below the value compare the variant with the base variant, i.e. they show the effect of the assumptions alone: a green cell is better, a red one is worse. The Current plan is only a reference, without colours - it does not count unplanned operations as late. The Delay change vs base row lists the orders whose delay the assumptions changed (e.g. “ZP/2026/0012 +18 h”).

Clicking a column shows the variant plan on the timeline: row = resource, blue - operations moved compared with the current plan, grey - unchanged, hatched - operations that stay (locked, running, frozen window), dashed frame - the current plan. The downtime window is red, extra work is green.

Save as proposal (only in OmniMES, after confirmation) creates a planning proposal with the variant assumptions. Approve in the Schedule opens the Schedule with the dialog of that proposal - then continue as in automatic planning. When approving, you choose whether downtimes and extra shifts go to the Resource calendar, and priorities and due dates - to the orders (see “Approving a proposal with what-if assumptions” above).

How downtime is calculated: an operation from the frozen window that falls on its resource's downtime leaves the frozen window and is planned again. Locked and running operations stay (marked as “during downtime”), and the forecast of running operations takes the downtime into account. The app remembers each user's variants in their private data.

Resource calendar

You set the working time of a resource in Production setup → Resource calendar: shifts (a resource takes its shifts from the closest level - machine, then line, park, finally the whole plant) and exceptions: extra shifts, holidays, maintenance and planned stops. The Resource availability section in the same tab shows the working week of each resource the way the Gantt calculates it. When there is no shift with ticked days in the system and Resource without shifts available around the clock is turned on in the module settings, the plan and the forecast treat resources as available 24 h.

Typical situations

  • An urgent order has to go before others - set its priority to Urgent in the order edit and create a new planning proposal, or drag its operations manually.

  • An operation has to stay where it is - turn on the Lock in the operation details.

  • The timeline shows a collision - move one of the operations or create a planning proposal.

  • Quality blocked a material lot - click Recalculate from now, check the comparison and approve the plan.

  • A machine will stop for maintenance - what about due dates? - in the What-if planner app add a “machine down” variant and compare it with the current plan; if needed, check an extra shift in a second variant.

  • The maintenance variant is good - how do I put it into effect? - save the variant as a proposal, click Approve in the Schedule and approve with Enter downtimes and extra shifts in the resource calendar selected - the maintenance goes to the calendar and the next planning run takes it into account.

Limitations

  • Automatic planning does not optimise the plan (no APS) - it arranges operations by priority and due date.

  • An operation can only be moved to a resource of the same type.

  • Plan changes do not change the order or operation status.