Production setup

Menu → Production → Production setup

Production setup holds the data the Production module works on: colours, routings, cycle time and changeover norms, the resource calendar (shifts, exceptions and availability), the dictionaries of pause reasons and defect codes, the rules for stop reasons from machine signals, work instructions for the operator panel, the module and traceability settings, labels and printers, and the switch from the old schedule.

The screen has 10 tabs: Colors, Routings, Norms and setups, Resource calendar, Dictionaries, Reasons from signals, Work instructions, Settings, Labels and printers and Switch from the old schedule. The order in which to fill them in during an implementation:

  1. Colors - the colour dictionary; you fill in the colour, standard price and minimum stock of items in the Item master.

  2. Routings - production stages of products or families.

  3. Norms and setups - norms for resources other than those in the routing, and the setup matrix.

  4. Resource calendar - shifts (working hours) and exceptions: holidays, maintenance, planned stops, extra shifts.

  5. Dictionaries - pause reasons and defect codes.

  6. Reasons from signals - automatic stop reasons.

  7. Work instructions - instructions for operators (can be added at any time).

  8. Settings (order module and traceability), and finally - when the plant kept orders in the former schedule - Switch from the old schedule.

Access and permissions

The Production setup item is in the Production menu in the OmniMES context. The administrator grants access in Access permissions. Changes in the tabs require write permission for the Production setup screen. With the update, groups that had the former Work time configuration screen received this screen (the Resource calendar tab), and groups with Production setup received the Item master screen (colour, price and minimum stock of an item).

Deleting a colour, routing, norm, matrix entry, reason, defect code or rule moves the item to the archive - historical data (orders, pauses, scrap) stays unchanged.

Colors

The colour dictionary, e.g. RAL paints: Code (e.g. RAL 3020), Name, Display color (from the palette or as a #RRGGBB code), Notes and Active. You assign colours to items in the Item master. The product colour appears in lists, on operator panel cards and on the Gantt, and a colour change between consecutive orders on a resource can mean a changeover (setup matrix).

Colour, price and minimum stock of an item

The former Bases and references tab no longer exists. You edit the Colour, Standard price and Minimum stock fields of an item together with the rest of the item data in System settings → Item master (the Item master chapter). The old address of that tab opens the item master.

Routings

A routing is a template of stages for a product or a product family. A new order gets a copy of the product routing or, if there is none, of its family routing. Changing a routing does not change existing orders.

The list shows the name, what the routing applies to, its stages and whether it is active. Row icons: Copy routing (a new routing with the suffix “(copy)”) and Delete routing. Clicking a row opens the routing for editing, Add routing - a new one.


Routing fields: Name, Applies to (For product with a product choice or For family with a family choice or entry), ERP identifier, Notes, Routing active.

Stages in order - for each stage:

Field

Meaning

No. and arrows

Stage order; the arrows move the stage up and down.

Stage name

E.g. Painting, Curing, Inspection, Packing.

Stage type

Machine work (cycle time norm and machine counter), Timed stage (minimum duration, e.g. curing), Manual work (e.g. packing, assembly), Inspection (scrap reported with a defect code).

Resource

Default machine or line of the stage. A timed stage may have no resource.

Norm [s/pc], Changeover [min]

Cycle time norm and changeover time of the stage.

Stage time [min]

Minimum time of a timed stage (required for this type).

Expanding a stage shows additional settings:

  • Stage parameters - name and value pairs (e.g. temperature, pressure, program); the operator sees them on the task card in the panel.

  • Consume BOM materials at this stage - BOM materials are consumed at one stage: the one marked here or, if none is marked, the first one. The issue for good and scrap quantities is recorded when the stage is finished, if BOM consumption is turned on in the module settings.

  • Notes.

  • The Traceability section: Material lot scan requirement, Stage materials, Stage creates a product lot - described in the Lots and genealogy chapter.

Norms and setups

Product × resource norms

The system picks the cycle time and changeover norm for an order operation in this order (first match wins):

  1. approved product norm on this resource for this stage,

  2. product norm on this resource for every stage,

  3. product family norm on this resource (first for the stage, then for every stage),

  4. norm from the routing stage.


The norms table shows the product or family, stage, resource, norm [s/pc], changeover [min], Source and Approval. Filter: All, Proposals, Approved; the To approve: n tag gives the number of proposals.

Norm sources:

Source

Where it comes from

Manual

A norm added with Add norm.

From ERP

A norm sent by the ERP (the erp-api API or a file on the ERP integrations screen) - approved at once; the resource follows from the work centre mapping of the integration. See the ERP integrations chapter.

Computed from production

A proposal from the Compute norms from production button.

Adding a norm: Add norm → choose For product or For family, the stage (empty = norm for every stage on this resource), a machine or line, enter the cycle time norm or the changeover time, optionally notes, select Approved (used in orders and planning) → Save norm.

Norms from production: Compute norms from production → enter Days back and Minimum number of lots → Compute proposals. The system computes the median working time without pauses per piece from finished lots (product × resource × stage). The result is proposals with a description of the basis (number of lots and pieces, s/pc range, period) - they do not change the norms in force until you click Approve in the row.

A norm applies to new operations. Operations of existing orders keep the norm they were created with; you change the norm of a single operation in the order details.

Setup matrix

Changeover time when the product colour or family changes on a resource: Attribute (Colour or Family), From value, To value (for a colour - the colour code, e.g. RAL 9010; for a family - the family name; “*” = any value), Resource (or Any resource), Time [min] and Notes.

  • Colour is checked first, then family; an entry for a specific resource wins over a general one.

  • The same colour or family without an entry = no changeover; no data = changeover from the norm.

The changeover from the matrix appears on the task card in the Operator panel (e.g. “Changeover: 35 min (colour change: …)”), on the Gantt and in automatic planning.

Resource calendar

The tab gathers the working time of resources in one place: shifts (working hours), exceptions (holidays, maintenance, planned stops, extra shifts) and an availability preview - when a resource actually works. The Schedule (Gantt), automatic planning, the order end forecast and OEE use this calendar.

The tab replaced the former System settings → Work time configuration screen. The shifts saved on that screen are here without moving them. Groups that had it received the Production setup screen with the update, and the old address opens this tab.


Shifts (working time)

The table shows the shifts: Name, Applies to (whole plant, park, line or machine), Days and hours (e.g. “Mon-Fri 06:00-14:00”) and Valid (a period or “no limit”). A shift without ticked days and dates has the inactive tag - the calendar skips it. Clicking a row opens the shift for editing, and the bin icon deletes it: the shift is archived and the resources stop using it.

Which resource uses which shift. A resource takes its shifts from the closest level: machine, then line, then park, finally the whole plant. A resource with its own shift does not use general shifts - a machine shift wins over a line shift, a line shift over a park shift, a park shift over a whole-plant shift.

Adding or changing a shift:

  1. Click Add shift or a shift row.

  2. Enter the Name (e.g. “Shift I”) and choose Applies to: Whole plant, a park, a line or a machine.

  3. Choose the mode:

    • Weekly - tick the days and enter the hours from - to. A day can have several hour ranges (+ adds a range). First day hours to the other days copies the hours to the ticked days, and Continuous work (24 h, 7 days) sets the whole day on every day.

    • Single dates - Add a period for each working period from - to, e.g. a Saturday with overtime.

  4. Optionally set Valid from and Valid until (inclusive) - empty fields mean no limit.

  5. Click Save shift.


00:00-00:00 means the whole day. An end earlier than the start is a shift over midnight, e.g. 22:00-06:00. Saving shifts requires write permission for Production setup.

Resources without working time

Once any shift has ticked days, a resource without its own shift (machine, line, park) and without a whole-plant shift does not work at all - not around the clock. Planning will not place operations on it, the end forecast grows and OEE has no planned time. That is why a warning appears at the top of the tab with the list of resources used in production (in operations, routings or norms) that have no working time in the next 7 days; when there are none - with the list of the other resources without working time.

  • Assign a shift to such a resource or add a whole-plant shift.

  • The Add a whole-plant “Continuous work” shift button adds a 00:00-00:00 shift on 7 days for the whole plant. It is shown when there is no whole-plant shift yet.

When there is no shift with ticked days in the system, a message at the top of the tab explains it: with the Resource without shifts available around the clock setting on (the Settings tab) all resources work around the clock, and with it off - no resource has working time. The first shift with days switches the around-the-clock work off for all resources.

Exceptions

An exception changes the working time at a specific time - for the whole plant, a line or a machine. You filter the exception list by a date range (From, To); the Hours column gives the length of the exception.

Exception kind

Meaning

Holiday / day off

Resource unavailable - this time does not count as planned operating time.

Maintenance

Resource unavailable due to maintenance - planned downtime, does not lower OEE availability.

Planned stop

Resource unavailable - planned stop, does not lower OEE availability.

Extra shift

Extra working time outside shifts, e.g. a Saturday with overtime.

Add exception → choose the resource (or Whole plant), the kind, the start and the end and notes → Save exception. Clicking a row opens the exception for editing, the bin icon deletes it.

Resource availability

The section shows where a resource takes its shifts from and how many hours it actually works. It is calculated by the same function as the Gantt, planning, the end forecast and OEE.


  • The resource table: Resource (with line and park), Shifts from (machine, line, park, whole plant, “24 h (no shifts)” or “none - does not work”) with the shift names, and Hours (7 days). The Only resources used in production field narrows the list to the resources of operations, routings and norms.

  • Clicking a resource shows its week: a bar for each day with the working time (Work), the Extra shift and the time Removed by an exception, the exceptions of that week, and the capacity: Available, Planned (order operations with a plan), Free and Utilization. The arrows and This week change the week.

In the screenshot: maintenance on Wednesday removes 4 hours from the shift, and an extra shift on Saturday extends work until 20:00.

Dictionaries


Pause and downtime reasons - the operator chooses a reason when pausing, and the signal rules and the reason corrections on the OEE (ISO 22400) tab (Analyse → Work time and OEE) use the same dictionary. Fields: Code, Name, Category, Parent reason (reason tree; reason groups in the Pareto) and Active.

Category

How it counts in OEE (ISO 22400)

Unplanned downtime

Lowers availability.

Planned stop

Reduces planned operating time, does not lower availability.

Changeover

Lowers availability; reported as a separate “setups” loss.

After installation the dictionary contains sample reasons (among others Awaria maszyny, Brak materiału, Brak operatora, Problem jakościowy, Przezbrojenie / zmiana koloru, Czyszczenie, Przerwa planowana, Konserwacja planowana, Inna przyczyna) - you can rename them.

Defect codes - describe the cause of scrap reported in the operator panel: Code, Name, Group (helps in Pareto analysis; in the panel the codes are grouped) and Active. Dictionary changes are recorded in the event log.

Reasons from signals

The tab has two parts: rules that assign a reason to machine stops, and a preview of the micro-stop thresholds.


Downtime reason from the machine signal

A rule assigns a reason to a machine stop without the operator. The system ranks the reason from an operator pause and a manual correction on the OEE (ISO 22400) tab (Analyse → Work time and OEE) above a rule. Without rules, machine stops without an operator pause are “unassigned”.

Rule source

When it matches

Code from a signal

Value of a separate signal (e.g. an alarm or stop code from the PLC) during the stop.

Machine status

The machine is in this status from the Status configurator (e.g. “Stop - no material”).

Event type

Any status of the event type (e.g. Failure) - a general rule, lowest priority.

Adding a rule:

  1. Click Add rule and choose the Source.

  2. Choose the Scope: All machines, a line or a machine.

  3. Set the condition:

    • for a status - Machine status (the list shows the event type and the status values),

    • for an event type - Event type,

    • for a code from a signal - Signal (tag) and Condition: Value (exact value, text or number, e.g. 17), Range (value in [from, to); an empty field = no limit), Any code (any non-zero and non-empty value) or Value = reason code (the PLC sends e.g. 17 and the dictionary reason has code 17).

  4. Choose the Reason (with the “Value = reason code” condition the reason comes from the signal value), optionally enter Notes and leave Active selected.

  5. Click Save rule.


Rule order: code from a signal, then status, then event type; within each source, the machine rule first, then the line, then all machines. For a code from a signal, the value at the start of the stop and its changes during the stop count (a PLC often sets the code a moment after stopping). A rule for a line or all machines takes the signal with the same tag from the status configuration of each machine.

Saving or deleting a rule recalculates OEE and Pareto of the last 7 days in the background. Recalculate older periods with Recalculate on the OEE (ISO 22400) tab (Analyse → Work time and OEE).

Micro-stops

A stop not longer than the threshold is a micro-stop: a performance loss (its time counts as production time), a separate row in the Pareto.

The micro-stop thresholds are set in one place for the whole system: System settings → Micro-stops (general threshold, highlighting of micro-stops and thresholds by event type). The Micro-stops section in this tab shows them for preview only:

  • General threshold (unplanned stops and failures) - the threshold in seconds, or “off (… s) - OEE without micro-stops from the general threshold” when micro-stop highlighting is off;

  • Threshold by event type - event types with their own threshold; an event type threshold wins over the general threshold.

The Change thresholds button opens the Micro-stops screen - it is shown to users whose group has this screen in the menu. Without this access the section says that the administrator changes the thresholds.

Previously this tab had its own micro-stop thresholds for OEE. With the update the system moved them to System settings → Micro-stops without changing the OEE figures, and groups with Production setup received access to that screen.

Work instructions

The Work instructions tab keeps versioned instructions for operators: machine operation, safety, quality and changeover. Operators see them in the Operator panel at the task they apply to.

The list shows the title and document number, the category, Applies to (where the instruction is in force), the state (In force, Waiting for date, Draft, Withdrawn) with the version number and the effective date, and a draft in preparation. Filters: text, category, state and resource.

Where an instruction applies

Instruction window, Instruction tab: Title, Document number (optional, e.g. IS-012), Category and the fields that narrow the instruction:

Field

Empty means

Example

Machine or line

any machine and line

A line instruction also applies on the machines of that line.

Product

any product

An instruction only for product REF-12.

Routing step

any step

The “Painting” step from the product routing.

Operation name

any operation

“Packing” - for orders without a routing, e.g. from ERP.

The fields can be combined freely, so e.g. a general paint booth instruction (machine only) and a detailed painting instruction for a product (product + step) apply side by side. An instruction without any field applies at all workstations.

Requires read confirmation - before the first task start after a new version is approved, the operator confirms in the panel that they have read it (who, when, which version).

Versions: draft, approval, withdrawal

  1. Draft - a new instruction starts with draft v1. In the Draft tab enter the content (formatting: # heading, **bold**, *italic*, link; the Preview switch shows what the operator will see), the Change description and add attachments: PDF (up to 20 MB), JPG, PNG, WEBP, GIF pictures (up to 10 MB) and MP4 video (up to 50 MB). Click Save draft.

  2. Approval - Approve version selects the In force from date (now or later). An approved version cannot be changed any more.

  3. Changing an instruction - New version (draft) copies the content and attachments of the version in force. After the new version is approved, the previous one becomes Superseded.

  • One version is in force at a time. A version approved with a future date waits (Waiting for date) - until then the previous one is in force. A second waiting version is not possible: withdraw the first one before.

  • Withdrawal - in the Version history, the Withdraw version button (with a reason). After withdrawal the operator does not see the instruction until a new version is approved - the previous one does not come back.

  • Deleting an instruction moves it to the archive; an instruction with an approved version must be withdrawn first.

Version history and comparison

The Version history tab shows each version: the state, In force from, who approved or withdrew it and when (with the reason), the change description, the number of attachments and Confirmations - who confirmed reading the version and when. The eye icon shows the version content, and Compare with previous shows the differences.

The Compare tab puts any two versions side by side: added (green) and removed (red) lines with line numbers of both versions, and added and removed attachments.

Permissions

  • Instructions and drafts are edited by a group with write permission for the Production setup screen.

  • Only a group with the Approve work instructions permission approves and withdraws versions (Administration → Access permissions, Production group). This permission is not a menu screen; after the update only the Administrators group has it. Without it the tab shows who approves.

  • Approval, withdrawal, creation, change and deletion of an instruction go to the Event log (Production category).

Settings

The Settings tab has three sections - Order module, Traceability and Order email notifications - and one Save settings button that saves all of them together; when any value is invalid, nothing is saved. Refresh reads the saved values. Below the sections is the Lot numbering patterns table.

The Settings tab combines the former Module settings and Traceability tabs. The old address of the “Traceability” tab opens Settings.


Order module

Group

Setting

Meaning

Orders

Order number prefix

Prefix of the number assigned by the system (e.g. ZP → ZP/2026/0001).


Machine piece counter

Event type with the piece counter. The counter quantity is a check of the operator report - shown next to it, it does not replace it.

Due date and planning

Margin for “at risk”

An order is at risk when the forecast end exceeds the due date minus this margin.


Frozen plan window

Automatic planning does not move operations that start within this time from now.


Planning horizon

Default range of automatic planning (days ahead).

Shop floor and stock

Time for the operator to correct a report

For this many minutes after saving (10 by default) the operator can correct their last quantity report in the operator panel. Later - only a supervisor with the Production orders permission. 0 = supervisor only.


Require a defect code for scrap

The operator cannot report scrap without choosing a defect code.


BOM material consumption

When a consuming stage is finished, the system records the issue of BOM materials for good and scrap quantities.


Resource without shifts available around the clock

When no shift with hours exists in the system, the plan and the forecast treat resources as available 24 h (the Resource calendar tab).

Traceability

The section contains the traceability settings: default scan requirement at a stage, consumption split with several lots, expiry warning, lot mass balance warning threshold, time for the operator to undo an entry, the reaction to an NOK inspection result, pause reason for a quality hold, order release without material, the reaction to an NOK result of a critical parameter, process alarm notifications and reasons for quality status changes. They are described in the Lots and genealogy chapter, and the quality inspection settings in the Quality chapter.

The Order release requires material setting applies to orders:

  • off (default) - releasing an order for which released material is missing only shows a warning,

  • on - missing released material stops the release; the order can be released deliberately with Release anyway, and the decision goes to the order history.

Order email notifications

An email when an order starts (first stage start) and when it is completed (all lots finished), to the people assigned to the order (the Notifications tab in the order details - chapter Production orders) and to the default recipients from this section.

Setting

Meaning

Send order email notifications

The switch for all order notifications (on by default - without recipients nothing is sent anyway).

When an order starts, When an order is completed

Which events send a message.

Language of messages to addresses outside the system

Polish or English. Accounts get the message in their interface language (saved at login and when the language is changed in the top bar).

OmniMES address in links

The address at which the recipients open OmniMES (e.g. https://omnimes.company.com) - the message then has the Open the order in OmniMES button. Use the current address enters the address at which you have the system open. Empty = message without a link.

Default recipients — accounts, Default recipients — addresses outside the system

They get messages about every order, in addition to the recipients set in the order.

The mail server is set in General configuration → Email. When mail is not configured, the notification has the skipped state with the reason.

Lot numbering patterns

The table below the sections: the numbering patterns of lots, pallets, recall cases and nonconformances, and a preview of the next number (Next number, Show next number). You add a pattern with Add pattern and save it in its dialog - independently of the Save settings button. The pattern tokens are described in the Lots and genealogy chapter.

Labels and printers

The Labels and printers tab is used to set up label templates (PDF, ZPL, GS1), label printers, reprint reasons and pallets after packing in the operator panel. See the Lots and genealogy chapter.

Switch from the old schedule

Production is the only order module and it is on in every installation - there is no module switch. The tab is used to move orders from the former schedule to Production; the old orders and their entries stay in the database as history. It is useful only where the plant kept orders in the former schedule.


Moving orders

The tiles show: Orders in the old schedule, Already moved, To move, Without product (will get the BEZ-INDEKSU item), Without quantity (will be skipped) and From ERP (keep the ERP link). Below is a list of up to 20 sample orders to move.

  • Each order becomes a Production order with one “Produkcja” stage on the machine or line of the order and one lot; good and scrap quantities come from the old order.

  • Production entries stay in the old module as history. An order moved once is not moved again.

  • Orders from ERP keep their link, so reports to the ERP reach the right order.

Click Move orders (n) and confirm. The result gives the number of moved, skipped and failed orders (with lists of the skipped orders and errors). The old orders stay unchanged.

Move the ERP orders that exist only in the former schedule. Until they are moved, changes from the ERP (due date, quantity, cancellation) go to the former order, which is no longer in the menu. New orders from the ERP always go to Production.

One order module

The block below the move reminds where the functions of the former module are:

  • orders, including ERP orders, are handled only in Production; the former schedule and order lists are not available in the menu, and groups that used them have Production orders and the Production calendar;

  • ERP orders are on the Production orders list with the Source: From ERP filter (formerly the ERP orders screen), and shifts and working time are in the Resource calendar tab;

  • the colour, standard price and minimum stock of an item are set in the Item master, and the lot list with filters is in Lots and genealogy.