Production calendar
Menu → Production → Production calendar
The Production calendar is an overview for the production manager: what is happening now and what is coming in the next days. It shows the orders or operations of the Production module in a calendar - planned work according to the plan, running and completed work according to the actual execution. Next to it is the Now in production panel with the lots being worked on right now. The colour shows at once which orders are at risk or overdue.
The screen only shows data - you change nothing here. You lay out the operation plan in the Schedule (Gantt) and manage orders in Production orders. Clicking an order in the calendar opens its details.
The Production calendar replaced the former Preview → Production schedule screen. Groups that had it received access to the Production calendar with the update, and the old address of the screen leads here.
Access and permissions
The Production calendar item is in the Production menu, right after Production orders. The administrator grants access in Access permissions. The screen only reads data, so it needs no write permission.
Opening an order from the calendar requires access to the Production orders screen. Without it, a click shows the message “No access to the “Production orders” screen.”, and the Open the schedule button appears only with access to the Schedule (Gantt).
On the Dashboard, the Now in production and today tile shows the same as the Now in production panel plus the operations planned for today; its title leads to the Production calendar.
Toolbar
Element | What it does |
|---|---|
Month, Week, Day | Calendar view (Week by default). The week and day views scroll to the current hour. |
arrows and Today | Previous period, back to today and next period. The selected period is shown next to them. |
Orders / Operations | Orders - one bar per order. Operations - each order stage on its resource. |
Refresh | Reads the data right away. The screen also refreshes itself every 60 seconds; the button tooltip gives the time of the last refresh. |
All parks, All lines, All resources | Park, line and resource (machine or line) filter. It applies to the calendar and to the Now in production panel. The list contains the resources with module operations. Clear filters returns to the whole plant. |
legend | State colours and markers (described below). |
The calendar remembers the view, mode and filters in the browser on this device.
What the calendar shows
The calendar shows orders that are released, in progress, completed and closed. Drafts and cancelled orders are not shown - they are not shop floor work yet (a draft is visible on the Gantt).
Order or operation | Bar in the calendar |
|---|---|
completed | from the actual start to the actual end |
running | from the actual start at least until now; an order - until the forecast end if it is later, an operation - until the end of its plan |
planned | according to the plan; a plan without an end - one hour from the start |
Orders - the bar shows the order number and the product code, and in the week and day views also the hours and the product name.
Operations - the bar shows the order number and the stage name, and in the week and day views also the hours and the resource.
In the month view a day shows up to four items, and the “+N more” link expands the rest. In the week and day views overlapping items are collapsed into a “+N” marker.
Clicking the date in a column header or a day number switches to the view of that day.
The red line in the week and day views is the current moment according to the OmniMES server time.
Released orders without a plan and without started work have no place in the calendar. Their number is given by the message below the calendar (“Released orders without a plan: …”) with the Open the schedule button - you plan them on the Gantt.
Colours and markers
Colour | State |
|---|---|
light blue | Planned - work has not started yet |
blue | In progress - work is running, the due date is not at risk |
orange | At risk - the forecast end of the order exceeds the due date minus the margin from the module settings |
red | Overdue - the due date has passed and the order is open |
light green | Completed |
An operation has the colour of the due state of its order: an operation of an order at risk is orange as well. The due state is described in the Production orders chapter.
Marker on the bar | Meaning |
|---|---|
play icon | work is in progress (work in progress in the legend) |
pause icon | work is paused (paused) |
ERP | order from the ERP (order from ERP) |
clock icon | the order was completed late |
In the screenshot: the Day view, the Operations mode, a filter on one park. Orange operations belong to orders at risk, red ones to overdue orders.
Tooltip
Hovering over a bar shows the details:
the order (with the ERP number), product and customer;
in the Orders mode - status, Good / quantity with the progress percentage and the stages done out of all, with the names of the current stages;
in the Operations mode - the stage with its number and status, the resource and the stage Good / quantity (with scrap);
Plan, Actual (from - to, or “in progress”), the due date with the due state and the forecast end (for orders not completed);
“Click to open the order.” - when you have access to Production orders.
Clicking a bar opens the order details on the Production orders screen.
Now in production
The panel on the right (on a narrow screen - above the calendar) shows the lots being worked on or paused, by resource. At the top are the counters In progress, Paused and Due date at risk. Items of overdue and at-risk orders come first.
Each item shows:
the resource and the lot status: In progress or Paused;
the order number with the ERP tag, the product code and name (a dot in the product colour);
the stage and the lot number;
the progress bar of the lot at the stage: done (good and scrap) out of the quantity that entered the stage, and for a timed stage - “timed stage until …”;
for a pause - the reason (or “no reason given”) and since when it lasts;
the due state (At risk, Overdue), the due date (forecast end in the tooltip), the start time and the operator.
Clicking an item opens the order. When nothing is running on the resources, the panel shows “Nothing is running on the resources right now.”
Typical situations
Briefing at the start of a shift - the Day view, the Operations mode and a park or line filter: you see what is planned for today on each resource, and in the panel - what is already running and what is stopped and why.
Which orders will not make it this week - the Week or Month view, the Orders mode: orange and red bars. The tooltip gives the due date and the forecast end.
An order is not in the calendar - check whether it is released (the calendar does not show drafts) and whether it has a plan or started work. Released orders without a plan are counted by the message below the calendar. A park, line or resource filter also hides stages without a resource (e.g. curing) - clear the filters.
The message “This period has a very large number of orders…” - the calendar shows up to 1500 orders at once. Choose a shorter period.
The message “There are no orders in the Production module yet…” - add an order in Production orders or move the orders of the former schedule (Production setup → Switch from the old schedule).
Limitations
The calendar only shows data. You change the plan on the Schedule (Gantt) and the order in Production orders.
Stages without a resource (e.g. curing) are visible only without a park, line and resource filter.
The working hours of resources (shifts, holidays, maintenance) are not marked in the calendar - the Gantt and Production setup → Resource calendar show them.