# Operator panel

:::tip
Menu → Production → Operator panel

:::

The **Operator panel** is the screen for a shop floor workstation - a tablet or kiosk computer at a machine, line or stage. It shows the **resource queue**: order lots waiting at this workstation or in work. The operator starts work, pauses it with a reason, reports good pieces and scrap, finishes the lot stage, runs curing and splits lots. Every action is an event from which the system sets the order status and calculates quantities, OEE and the forecast.

The panel queue is the same queue shown on the **Schedule (Gantt)** and in the order details on the **Production orders** screen. Large buttons and the on-screen numeric keypad make it easy to use with a finger.

## Access and permissions

The **Operator panel** item is in the **Production** menu in the **OmniMES** context. The administrator grants access in [**Access permissions**](https://docs.omnimes.com/doc/administration-IPR8voQzB6).

* Panel actions require write permission for the **Operator panel** or **Production orders** screen. Without it the panel shows the queue as a preview only (“Queue preview — you have no permission for operator panel actions.”).
* A shared kiosk account is usually logged in at the workstation, and operators identify themselves with a code (described below).

## Choosing a workstation

When the panel opens, you choose the workstation: **Machines**, **Lines** or **Stages without a resource** (e.g. curing). Each tile shows the number of tasks in the queue. The search field filters machines, lines and stages.

 ![](https://docs.omnimes.com/api/files.get?sig=eyJhbGciOiJIUzI1NiIsInR5cCI6IkpXVCJ9.eyJrZXkiOiJ1cGxvYWRzLzRlMDdmZmNhLThmZjAtNDYxYy1iYjEyLTA2OTEyZGRiOGQzNi9kNWVkYzVmNC0yZjE5LTQwZTMtOTJmYy02YzA3ZWJhMjAyNTQvcG5fc3Rhbm93aXNrYS5wbmciLCJ0eXBlIjoiYXR0YWNobWVudCIsImlhdCI6MTc5NTQxMDAwMCwiZXhwIjoxNzk1NDk2NDAwfQ.xJAyrX73FF3E6PgRhxFNbcQRYFvZQqWSLte1gOD23FE " =1312x640")

The panel remembers the choice on this device - after the page is refreshed, it returns to the same workstation. You change the workstation with **Change workstation**.


:::info
A kiosk can open directly on a given workstation by adding a parameter to the screen address: `?resource=m:<machine id>` (line: `l:<line id>`) or `?stage=<stage name>`, e.g. `/mes-panel?stage=Sezonowanie`.

:::

## Workstation header

The header shows the workstation type and name (for a machine also its line) and - for a machine with a state signal - the **machine state** with its duration: Running, Unplanned downtime, Failure, Planned stop or Other state. A machine without a signal shows “No machine state signal”.

The panel refreshes itself every 15 seconds; the time of the last refresh is shown next to **Refresh**. When the connection is lost, the panel shows the time of the last data and keeps the data from the last read.

### Operator identification

In the **Operator code** field the operator taps an RFID card or enters a PIN and clicks **Sign in operator**. The code is the value of the **RFID** field in the user profile (Administration → Users). The RFID reader also works without clicking into the field: tapping a new card changes the operator. **Sign out operator** ends the identification.

The operator code is optional. Without it, actions are recorded for the account logged in to the browser. The operator name goes to the order and lot history.


:::info
**Operator code protection.** After 10 failed codes within 15 minutes at one workstation (panel account), new operator codes are locked for 5 minutes. Each further lockout within a day lasts twice as long. An unrecognised barcode scanned in the scan field also counts as a failed attempt. Operators recognised at this workstation in the last 12 hours keep working. The panel shows a message with the lockout time. An administrator removes the lockout: Administration → Users, the workstation account, **Unlock**.

:::

### Working time on the order

The panel records who worked on the order and for how long - this gives the **operator working time** (man-hours) in the order details, in the “Order progress” report and in the report to the ERP.

* **Login at the workstation** - when an operator logs in with a card or PIN at a workstation with exactly one task in progress or paused, the panel starts their work on that order right away (“Logged in to order …”). When several tasks are in progress, the operator chooses the task with the button.
* **Start work** on the task card (for a task in progress or paused; for a queued task - **More actions**) - starts work on the order of the task.
* **End work** - on the task card or in the “You are working on order …” bar below the operator field (the bar shows the order, the stage and the time since the start).
* The task card shows who is working on the order now (**Working on the order**).

Work ends automatically:

* when the **operator logs out** of the panel (or another operator's card is tapped) and when the account logs out of OmniMES,
* at the **end of the shift** from the resource calendar (Production setup → **Resource calendar**) - at the end time of the shift in which the operator started; shifts 06-14 and 14-22 are two shifts,
* when the operator **starts work on another order or stage** - the previous work ends at the same moment, so the time is not counted twice,
* when the **stage or the order is finished**.


:::info
Without an operator code, work is recorded for the account logged in to the browser. A resource without a shift calendar (around-the-clock work) does not end work from the calendar - then the button, logout or the end of the stage ends it.

:::

### Reporting a failure

On a machine workstation the **Report a failure** button opens a request to maintenance: type (failure, defect, other), priority, description, **Machine stopped**, a photo from the tablet camera and - when the machine is in a stop - **Link with the current stop** (failure start = stop start). The reporter is the operator signed in with their code. Below the button the panel shows the open requests of the machine with the work order status; after the repair the operator clicks **Confirm the fix** or **Not fixed** (with a description - the order goes back to the technician). Description - the [**Maintenance**](https://docs.omnimes.com/doc/maintenance-mfXqYdhBue) chapter.

## Queue: Current and Next

 ![](https://docs.omnimes.com/api/files.get?sig=eyJhbGciOiJIUzI1NiIsInR5cCI6IkpXVCJ9.eyJrZXkiOiJ1cGxvYWRzLzRlMDdmZmNhLThmZjAtNDYxYy1iYjEyLTA2OTEyZGRiOGQzNi8yMDg4YjY0ZS1hMDIxLTQwNjctYTkyNS02ZjYwYzg4MzcwYWEvcG5fa29sZWprYS5wbmciLCJ0eXBlIjoiYXR0YWNobWVudCIsImlhdCI6MTc5NTQxMDAwMCwiZXhwIjoxNzk1NDk2NDAwfQ.o5bke6uJnM-K_ISsmx9Yem8NqKkMPvdpZsEcNCntyKE " =1312x1250")

* **Current** - tasks in progress and paused. When nothing is in progress, the panel suggests starting the first task from the **Next** list.
* **Next** - lots waiting at this workstation, in queue order.

A task is an order lot at a stage. The task card shows:

| Element | Meaning |
|---------|---------|
| Order and lot number | The lot number opens the lot card. |
| Tags    | Status (Waiting, Running, Paused), priority, due date at risk, material availability, quality status of a lot held by quality. |
| Product and colour | Product code, name and colour; the stripe on the side of the card has the product colour. |
| Stage   | Stage name and type. |
| **Changeover** | Changeover time compared with the previous task at the workstation and its cause, e.g. colour change: RAL 9005 → RAL 3020. |
| **Lot quantity**, **Good so far**, **Scrap so far**, **Remaining** | Lot quantities at this stage. |
| **Working time** | Working time on the lot without pauses. |
| Due date, customer, **Plan**, **Waiting since**, start, operator, **Order** | Order and task data. |
| Stage parameters | Parameters from the routing, e.g. temperature or program. |
| **Instructions (N)** | Work instructions in force for the task; the **Confirm the instruction before start** tag when an instruction requires confirmation (described below). |

The material tag (**Material available**, **Material short**, **Material in quarantine**, **Material blocked**) is calculated by the same function as in the order and on the Gantt - the tags are described in the [**Production orders**](https://docs.omnimes.com/doc/production-orders-kiarXNCMN7) chapter, section “Materials”.

## Working on a lot

The **card buttons** depend on the task status:

| Status | Buttons |
|--------|---------|
| **Waiting** | **Start** (timed stage: **Start seasoning**) and **More actions** (⋮): **Split lot**, and for manual work and inspection also **Finish stage without start**. |
| **Running** | **Pause**, **Report quantity**, **Finish stage**. Timed stage: **Finish seasoning**. |
| **Paused** | **Report quantity**, **Finish stage**, **Resume**. |

### Start

Click **Start**. The panel confirms the start. When the lot or its material is held by quality, the start is blocked and the panel gives the reason. When a work instruction requires a read confirmation, the panel shows it first - see [Work instructions](#h-work-instructions).

### Pause


1. Click **Pause**.
2. Tap the downtime reason. The reasons are grouped by category (Unplanned downtime, Planned stop, Changeover); a child reason shows its parent reason below its name.
3. Optionally enter a note and click **Pause work**.

 ![](https://docs.omnimes.com/api/files.get?sig=eyJhbGciOiJIUzI1NiIsInR5cCI6IkpXVCJ9.eyJrZXkiOiJ1cGxvYWRzLzRlMDdmZmNhLThmZjAtNDYxYy1iYjEyLTA2OTEyZGRiOGQzNi9hNjk5ZmQwMi02NTVhLTQ1NjgtODgxZi00MzdjY2FhYzdjOGQvcG5fcGF1emEucG5nIiwidHlwZSI6ImF0dGFjaG1lbnQiLCJpYXQiOjE3OTU0MTAwMDAsImV4cCI6MTc5NTQ5NjQwMH0.lGfHT9jfXFYA5DfnlRyLrUx3t8ekWudS4kMdhu4y3eM " =624x546")

The reason is used in loss reports and OEE. For a machine with a state signal, the reason of the operator pause becomes the reason of the machine stop at the same time. When the reason dictionary is empty, the pause is saved without a reason - you add reasons in Production setup → **Dictionaries**. You continue the work with **Resume**.

### Quantity report

**Report quantity** records good pieces and scrap during work, without finishing the stage.


1. Click **Report quantity**.
2. Enter **Good** and **Scrap** (on-screen numeric keypad).
3. For scrap, choose the **Defect code**. When **Require a defect code for scrap** is turned on in the module settings, the code is mandatory.
4. Click **Save report**.

 ![](https://docs.omnimes.com/api/files.get?sig=eyJhbGciOiJIUzI1NiIsInR5cCI6IkpXVCJ9.eyJrZXkiOiJ1cGxvYWRzLzRlMDdmZmNhLThmZjAtNDYxYy1iYjEyLTA2OTEyZGRiOGQzNi8zMDk4YTI5ZC1iNjc0LTQyNjEtYjQwYi02ZDY2ZDA1OGNjYjMvcG5fbWVsZHVuZWsucG5nIiwidHlwZSI6ImF0dGFjaG1lbnQiLCJpYXQiOjE3OTU0MTAwMDAsImV4cCI6MTc5NTQ5NjQwMH0.pAZ0MBGZvmzgovqu-B3qmZENb5X63G8MzSWmCSrBdUU " =720x698")

The dialog shows the lot quantity, good and scrap so far, the state after saving and the **Machine counter** - the quantity from the machine piece counter during the stage. The counter is a check of the report: it is shown next to it but does not replace the operator report. Good and scrap cannot exceed the lot quantity at the stage - when they do, the dialog shows a warning.

Defect codes are grouped (e.g. Wygląd, Mechaniczne); you choose a code by tapping it. **Set scrap aside for rework** creates a rework lot from the scrap - described in the [**Lots and genealogy**](https://docs.omnimes.com/doc/lots-and-genealogy-NOoW4md8AC) chapter.

### Finishing a stage


1. Click **Finish stage**.
2. Enter **Good now** and **Scrap now** (with a defect code). An empty “Good now” field means that everything not reported as scrap moves on as good.
3. Check the summary **On the stage after saving:** - when some pieces are not accounted for, the panel warns that they will not move to the next stage.
4. Save.

Good pieces move to the queue of the next stage, and scrap stays at the stage. After the last stage the lot is finished and its good pieces are finished goods. When the stage creates a product lot (packing), the dialog lets you add the pieces to an existing product lot or create a new one - described in the [**Lots and genealogy**](https://docs.omnimes.com/doc/lots-and-genealogy-NOoW4md8AC) chapter.

### Correcting the last report

The **Correct last report** button appears in the panel header when the workstation has a quantity report or a finished stage saved in the last 10 minutes. This time is set in Production setup → **Settings** → **Time for the operator to correct a report**.


1. Click **Correct last report**.
2. When the workstation has several such reports, choose the right one (time, lot, stage, type, operator). The panel preselects the latest report of the identified operator.
3. Enter the correct **Good** and **Scrap** of this report - these are the values of the report, not the stage totals. For scrap, choose the defect code.
4. Optionally enter the reason and click **Save correction**.

The dialog shows how much time is left for the correction, the values of the report and the stage state after the correction.

* **Who corrects:** the operator - only their own report and only within the time window. A supervisor (permission to the **Production orders** screen) - a report of any operator, also after the time window, then with a mandatory reason. The supervisor corrects in the panel (logged in or with an operator code) or in the order details, on the **History** tab (pencil icon next to the last report of a stage).
* **Only the last report** of a lot at a stage. A later report or a finished stage closes the correction of an earlier one.
* **What the correction changes:** the stage and order quantities. Correcting a finished stage also changes the quantity passed to the next stage, finished goods and the product lot stock, and the recipe material consumption (in proportion to good and scrap). Corrected quantities count in OEE (quality), production and scrap reports and in the report to the ERP.
* **When it cannot be corrected:** the next stage of the lot has already started; the correction would change whether the lot moves on (good to zero or from zero); the scrap has already been set aside for rework; the order is closed or cancelled; the order is posted directly in the ERP and the correction would reduce a quantity already sent to the ERP (such a change is made in the ERP).


:::info
The original report stays in the history. The correction is a separate **Report corrected** entry with the values before and after, visible in the order history and in the **Event log**.

:::

### Curing (timed stage)

* **Start seasoning** records the start; the card counts down **Until the end of seasoning** and shows when the minimum time ends.
* When the minimum time has passed, the card shows “Minimum time has passed” and the **Finish seasoning** button is highlighted.
* Finishing before the minimum time requires the confirmation **Finish anyway** and is recorded in the history as finished before the minimum time.

### Splitting a lot

**More actions → Split lot** separates a new lot with the given quantity from a waiting lot. The new lot waits in the same queue, and the rest stays in the current lot. The new lot quantity must be greater than zero and less than the lot quantity.

### Messages and undo

The panel shows the result of an action in a full-width bar: green (success), orange (warning) or red (error, e.g. a blocked start). Green and orange bars disappear by themselves, a red bar stays until tapped. After loading or unloading a material lot, the bar has an **Undo** button that reverts this entry.

## Work instructions

Work instructions (operation, safety, quality, changeover) are prepared and approved by a supervisor in Production setup → **Work instructions**. At a task the panel shows only the **approved versions in force** of instructions that apply to the task: the machine or line of the workstation, the product, the routing step or the operation name. A task can have several instructions, e.g. a general machine instruction and a detailed painting instruction for a given product.

* The **Instructions (N)** button on the task card opens the list of instructions; N is their number. The button also works without permission for panel actions (view only).
* The list starts with safety and changeover instructions, then operation and quality. Tapping an instruction expands its content, version number, effective date and change description.
* Attachments: pictures are shown at once (tap to enlarge), a PDF opens with **Show** (when the tablet browser does not show PDF inside the page - **Open in a new tab**), a video plays with **Play**.

### Read confirmation

An instruction can require a read confirmation. Then the card of a waiting task shows the **Confirm the instruction before start** tag, and **Start** opens a window with the instructions to read.


1. Read the instructions marked **Requires confirmation**.
2. Click **Confirm and start** - the panel saves the confirmation and starts the task.

* The confirmation is saved for the person (the operator from the code, and without a code - the account logged in to the panel), the instruction version and the time. The supervisor sees it in the version history of the instruction.
* You confirm a version once. Further tasks of the same person start without asking until the supervisor approves a new version of the instruction - then at the first task start the panel asks to confirm the new version.
* Each operator confirms for themselves - changing the operator in the panel (code) means a new confirmation.
* You can also confirm instructions without starting: **Instructions (N)** → **I have read it** at the instruction (or **I have read all**).
* The same applies to **Finish stage without start** - when an instruction requires confirmation, the panel shows the instructions first.

## Materials, lot scanning and inspection

When the stage consumes recipe materials, the task card shows the stage materials, and a lot scan field appears in the panel header. The operator scans a material lot, loads it at the workstation or unloads it (FEFO suggestion, lots in quarantine). At an inspection stage, the **Measurements** button opens the measurement results of the inspection plan. These functions are described in the [**Lots and genealogy**](https://docs.omnimes.com/doc/lots-and-genealogy-NOoW4md8AC) and [**Quality**](https://docs.omnimes.com/doc/quality-vouKxxB9Wn) chapters.

## Typical situations

* **The queue is empty** - a task appears when the planner releases an order or a lot moves from the previous stage.
* **The operator forgot to press Start for manual work** - **More actions → Finish stage without start** (manual work and inspection).
* **Part of the lot has to be made later** - split the lot before starting.
* **The machine counter shows a different quantity than the report** - check the report before finishing the stage; the counter does not change the report by itself.
* **A mistake in a report** - **Correct last report** within 10 minutes of saving it; later ask a supervisor.
* **Start opens a window with instructions** - an instruction requires confirmation, and you (or the operator from the code) have not confirmed the version in force yet. Read it and click **Confirm and start**.
* **No Instructions button** - the task has no approved instruction; a draft or a version with a future effective date is not visible in the panel.

## Limitations

* The panel does not change the plan or the order stages - the planner does that on the **Production orders** and **Schedule (Gantt)** screens.
* The machine counter is shown only when a **Machine piece counter** is selected in the module settings and the machine has such a counter.

---

**Documents**

- [OmniPlatform](https://docs.omnimes.com/s/cb8b19e0-ec6d-4e1a-8690-b0ddd67ad1cd/doc/omniplatform-7z9SIECi68)
- [Omnienergy](https://docs.omnimes.com/s/cb8b19e0-ec6d-4e1a-8690-b0ddd67ad1cd/doc/omnienergy-56aRDgnYFZ)
- [Omnimes](https://docs.omnimes.com/s/cb8b19e0-ec6d-4e1a-8690-b0ddd67ad1cd/doc/omnimes-eGDa0U5cyr)
- [FAQ](https://docs.omnimes.com/s/cb8b19e0-ec6d-4e1a-8690-b0ddd67ad1cd/doc/faq-IFQjCNYt1Q)
- [Cybersecurity & Compliance (CRA)](https://docs.omnimes.com/s/cb8b19e0-ec6d-4e1a-8690-b0ddd67ad1cd/doc/cybersecurity-compliance-cra-pPJBcC6sBf)