Maintenance
Menu → Maintenance → Maintenance · My work orders · Machine events · Alarms
The Maintenance module takes a failure from the request to the confirmed fix: the operator reports a failure from the panel at the machine, maintenance gets a notification, the manager accepts the request and assigns a technician, the technician records working time, used parts and the work done, and production confirms that the machine runs again. The same module plans inspections by calendar or running hours, creates their orders ahead of time, calculates MTBF and MTTR from failure requests and shows the history of every machine.
Access and permissions
The Maintenance group is in the menu right after the Production group and has four screens:
Screen | For | What you can do |
|---|---|---|
Maintenance | maintenance manager | everything: requests, work orders, inspections, machines, MTBF/MTTR, dictionaries, settings and notifications |
My work orders | technician | orders assigned to the technician and their group: work, parts, notes, photos, completion; reporting a failure |
maintenance, production | one machine timeline: failures and stops with reasons (the same as in OEE), alarms, requests and work orders, operator pauses; notes on events, reporting a failure from a specific stop, CSV export (formerly History events in the Preview group) | |
maintenance | machine and system alarms, rules, notification channels (formerly in the Preview group) |
Everyone with the Operator panel or Production orders screen can also report a failure - the same people confirm the fix. After the update both screens are available to the Admins group; an administrator grants them to other groups on the Access screen. The menu is stored at sign-in - the new items appear after you sign in again.
After the update the system sends no notifications about requests or inspections until the manager sets the recipients on the Dictionaries and settings → Maintenance notifications tab.
How a failure is handled
Request - the operator clicks Report a failure in the operator panel (or the manager or a technician on their screen). The request gets a number, e.g.
ZG/2026/0007.Notification - the selected people get a notification in the bell and by e-mail. When nobody accepts the request, the system reminds them at the set interval.
Acceptance - the manager accepts the request: a work order is created, e.g.
ZS/2026/0012, assigned to a technician or a group.Work - the technician starts work, puts the order on hold if needed (e.g. waiting for parts), adds parts and notes.
Completion - the technician chooses the cause and the action, describes the work done and enters since when the machine runs again.
Confirmation - production confirms the fix in the operator panel. The order and the request close. When the machine still does not work, the operator chooses Not fixed and the order goes back to the technician.
Reporting a failure
From the operator panel
On a machine workstation, below the operator data, there is a Report a failure button.
Click Report a failure.
Choose the type: Failure (the machine stopped or cannot run), Defect (it runs with a problem) or Other.
Choose the priority: critical, high, normal or low.
Describe the problem - the first line of the description becomes the request title.
Tick Machine stopped if the machine does not run.
When the machine is in a stop right now, the panel offers Link with the current stop - the failure start will equal the start of the stop from the machine signal. Instead you can choose an open alarm of the machine (e.g. a stop longer than 15 minutes).
Add a photo - the tablet camera opens.
Click Send request.
The reporter is the operator signed in to the panel with their code. When the machine already has an open request from the last 24 hours, the panel asks whether to add a new one - the Add anyway button.
Below the button the panel shows the open requests of the machine with the order status and the technician. When the technician finishes the work, the request shows Confirm the fix and Not fixed (with a description of what still does not work).
From the Maintenance screen
Requests tab → Report a failure: the same form with a machine choice. A technician reports a failure from the My work orders screen.
Requests
The Requests tab lists the requests - open ones (new and accepted) by default. Filters: state, type, machine, text. The Failure time column shows how long the failure lasts (or lasted).
Action | When | What it does |
|---|---|---|
Accept | new request | creates a work order: technician, group, priority, due date; Start work now records your working time |
Reject | new request | with a reason, e.g. a duplicated request |
Close without an order | new request | when the problem was fixed without a technician - failure end = now |
Clicking a row opens the details: description, who reported it and from where, failure time, linked stop, photos and history.
Work orders
The Work orders tab has two views:
List - scopes: open and awaiting confirmation, open, mine, overdue, closed and rejected, all; filters for type, machine and text.
Kanban - status columns: new, accepted, in progress, on hold, finished. Dragging a card from New to Accepted accepts the order, to In progress - starts or resumes the work. Putting on hold and finishing open the order window, because they need a reason or a cause.
The manager creates a New order manually (failure or other, e.g. an upgrade); inspection orders come from planned inspections.
Statuses
Status | Meaning |
|---|---|
New | waiting for acceptance |
Accepted | assigned, work not started |
In progress | a technician is working |
On hold | with a reason, e.g. waiting for parts |
Finished | work done - waiting for confirmation by production |
Closed | confirmed by production or closed by the maintenance manager |
Rejected | with a reason |
Order window
Clicking an order opens a window with action buttons depending on the status and tabs:
Details - description, request (who, when, failure time, linked stop), assignment, due date; work details: cause and action from the dictionaries, work done, checklist (for an inspection - from the plan) with notes. Save work details button.
Working time - technician entries: start and end, duration, entry from the button or manual. Several technicians can work on one order at the same time. The manager can start work for a chosen technician and delete entries; Add manual entry - when someone worked without a tablet.
Parts - Add part: an item from the item master (the suggestion shows the stock; with Issue from stock ticked the part is taken off the stock) or a manually entered item (quantity only). Deleting an item-master part returns it to the stock. The part value is an estimate at the standard price from the item master.
History and notes - all changes of the order and the request; a note field.
Attachments - photos (with a preview) and documents; download and upload.
A technician changes only the work details in an order (cause, action, work done, checklist) and their own working time. Assignment, priority, due dates, rejection, closing and reopening belong to the maintenance manager.
Finishing
Finish order opens a window: cause and action (required for a failure - the setting can be switched off), work done and Machine running again since - the failure end in the request that MTTR is calculated from (now by default). For an hour-based inspection you can enter the meter reading; an empty field = the machine meter reading. Finishing stops the work of all technicians on the order.
Confirmation and closing
A finished order is closed by confirmation by production - in the operator panel or in the order window (Confirm the fix). Not fixed with a description returns the order to work and the failure continues. The maintenance manager can close a finished order alone (Close) - the history keeps who closed it. Reopen returns a finished or closed order to work.
My work orders (technician view)
A tablet screen at the machine: order cards with large Start work / Stop my work, Put on hold, Resume, Finish order and Details buttons (order window: parts, notes, photos).
Scope | What it shows |
|---|---|
Mine and my group | orders assigned to the technician, orders of their group without a technician and orders the technician is working on |
All open | orders to take |
Awaiting confirmation | finished, waiting for production |
Starting work on another order stops the work on the previous one.
Planned inspections
The Inspections tab lists inspections with the due date status: On schedule, Approaching (lead period), Overdue, No meter.
Add inspection:
Due by calendar - every N days, weeks or months; next due date; lead time in days. Next due date: fixed rhythm (from the previous due date, e.g. always the first Monday) or from completion (e.g. 3 months after the last inspection).
Due by running hours - every N running hours of the machine; lead in hours; meter reading at the last inspection (empty = meter now). A machine without a meter gets one automatically.
Checklist - one task per line; it goes to the inspection order as a list to tick.
Priority, technician, group, estimated time; Create the order automatically in the lead period.
The inspection order is created automatically when the inspection enters its lead period (the system checks every 15 minutes) - at most one open order per inspection. Buttons: Create due orders (at once for all in the lead period), and on an inspection Create order now (also earlier) and Skip due date (the inspection moves to the next due date). Finishing an inspection order moves the due date; rejecting an inspection order = skipping the due date.
The Calendar view shows a month: the next due dates of calendar inspections, the forecast day of hour-based inspections (from the machine work in the last 14 days, marked ~) and inspection orders (a click opens the order).
Hour meter
The meter is set on the machine card (Set the meter):
Machine states - the time the machine spent in the chosen states (Work by default) - from the machine state signal, the same as Monitoring and OEE. Count from the chosen day (at most 400 days back).
Counter signal - the value of an hour counter from the chosen machine signal in hours, minutes or seconds.
Initial reading - running hours before the meter was enabled, e.g. from the machine plate.
Machines and machine history
The Machines tab lists the machines with open requests, orders, overdue and approaching inspections and the date of the last failure (the Needing attention scope shows only such machines). A click opens the machine card:
hour meter, MTBF and MTTR from the last 90 days, number of orders and failures in the year, technician work and parts value,
inspections with the due date status, open requests and orders,
parts used in the last year,
Machine history - a timeline of requests, orders, status changes, work, parts, notes and inspections in the chosen period; also notes on machine events written on the Machine events screen (with the name and time of the event they concern).
The full machine timeline - with states, stops with reasons, alarms and operator pauses - is on the Machine events screen. From there you can also report a failure from a specific stop (also a finished one) - the failure start in the request is the start of that stop.
MTBF and MTTR
The MTBF / MTTR tab calculates reliability indicators from failure requests - with the same function as the telemetry MTBF/MTTR in Analysis → Work time and OEE:
failure - a request of type Failure (defects and rejected requests do not count); two requests of the same failure count once,
failure time - from the start of the stop (or the request) to the moment the machine runs again, clipped to the period,
n - failures started in the period,
MTTR = failure time / n, MTTF = operating time / n, MTBF = MTTR + MTTF,
operating time - from the machine state signal, otherwise from the shift calendar minus failures.
The Compare with telemetry option adds a column with MTBF and MTTR calculated from the stops in the machine signal.
The indicators API returns the same result: GET /mes-oee/reliability/?source=ur (without source - from telemetry, as before).
Dictionaries and settings
Maintenance notifications - recipient groups, users, extra e-mail addresses, channels (bell, e-mail) and a reminder when nobody accepted the request. Saving creates two rules on the Alarms screen: new failure requests and inspections approaching or overdue. Change the rule details (mute periods, severity, machine scope) on the Alarms screen.
Settings - request and order number prefixes, labour rate per hour (empty = cost without labour), currency, duplicate question window, issuing parts from stock, cause and action required for a failure, closing a failure order by production confirmation.
Causes and Actions - dictionaries with a code and a name; the system has starter dictionaries (e.g. mechanical wear, electrical fault; part replacement, adjustment).
Reports
Reports → Generate report → Maintenance:
Report | Contents |
|---|---|
Failures and MTBF/MTTR | for each machine: requests, failures, failure time, MTTR, MTTF, MTBF, availability |
Inspection compliance | inspection orders due in the period: completion, on time or late, delay, technician, working time |
Maintenance cost | for each machine: orders finished in the period, labour hours, labour cost (when a rate is set), parts |
Reports can be downloaded as CSV, sent by e-mail, saved in the archive and set up as recurring reports.
Event log
Requests, acceptances, order status changes, work entries, parts and skipped inspections go to the Event log in the Production category, and changes of inspections, dictionaries, meters and settings - in the Configuration category.
Limitations
An inspection does not block the machine in the resource calendar - production planning does not know about it until you add a stop in Production setup → Resource calendar.
A spare part is any item of the item master; the item master has no separate “spare part” type.
MTBF and MTTR from requests count calendar time (the whole day), not shift time.
A reminder goes to the same recipients - handing over to the next person (escalation) is a separate rule on the Alarms screen.